[G.R. No. 170732, October 11, 2012, 684 SCRA 55]
DOCTRINE:
Liquidated
damages – The
parties to a contract are allowed to stipulate
on liquidated damages to be paid in case of breach. It is attached to
an obligation in order to ensure performance and has a double
function: (1) to provide for liquidated damages, and (2) to
strengthen the coercive force of the obligation by the threat of
greater responsibility in the event of breach. As a pre-condition to
such award, however, there must be proof of the fact of delay in the
performance of the obligation.
Effect
of default –
As long as the contractor fails to finish the works within the period
agreed upon by the parties without justifiable reason and after the
owner makes a demand, then liability for damages as a consequence of
such default arises.
FACTS:
Respondent
Herbal Cove Realty Corporation (Herbal Cove) wanted to build a a
subdivision project somewhere in Tagaytay City. It hired petitioner
Atlantic Erectors Inc. (Atlantic) to build the project. The
Construction
Contract indicated
a contract price of almost P16.7Million and to finish building within
180 days. To secure payment in case of non completion of the
project, the contract also provides:
ARTICLE
IX
FAILURE
TO COMPLETE WORK
Section
1: The CONTRACTOR acknowledges that the OWNER shall not suffer [loss]
by the delay or failure of the CONTRACTOR to finish and complete the
works called for under this Contract within the time stipulated in
Section 6, Article IV. The CONTRACTOR hereby expresses covenants and
agrees to pay to the Owner liquidated
damages equivalent to the One-Tenth of One Percent (1/10 of 1%) of
the Contract Price per calendar day of delay until completion,
delivery and acceptance of the said Works by the OWNER to a maximum
amount not to exceed 10%.
Atlantic was asked to commence construction on July 8, 1996, but eventually, it asked for an extension citing bad weather and delayed
turnover of project sites which Herbal Cove granted but ultimately,
Atlantic failed to deliver. Herbal Cove terminated the contract on October 3, 1997 and
demanded liquidated damages. Herbal Cove also hired another
contractor to finish the job. It filed a case with the Construction
Industry Arbitration Commission (CIAC). The CIAC found in favor of
Herbal Cove but did not award liquidated damages for failure to
comply with 15-day notice of termination (provided for in its
contract.). The CA awarded liquidated damages.
ISSUE:
Whether
or not Atlantic is liable for liquidated damages.
HELD:
Yes.
The CIAC disallowed liquidated damages because Herbal Cove failed to
comply with the rule on notice. However, the contract is the law
between the parties and there are provisions in the same contract
which provide "the Contractor shall be required to pay the Owner
the liquidated damages in the amount stipulated in the Contract
Agreement, the said payment to be made as liquidated damages, and not
by way of penalty. The Owner may deduct from any sum due or to become
due the Contractor any sums accruing for liquidated damages as herein
stated." also, "Neither the taking over by the Owner of the
work for completion by administration nor the re-letting of the same
to another Contractor shall be construed as a waiver of the Owner’s
rights to recover damages against the original Contractor and/or his
sureties for the failure to complete the work as stipulated."
Thus, under the contract, Herbal Cove's right to liquidated damages
is distinct from the right to terminate contract.
No comments:
Post a Comment